UPDATE: I-91 Rockingham Bridge construction schedule
Press release | Aug 21, 2017 | Comments 0
The Vermont Agency of Transportation has begun replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of Aug. 21, 2017.
I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.
I-91 activities:
Monday thru Friday:
- Continue removing the existing northbound bridge deck slabs and floor beams from the first span.
- Begin constructing upper retaining wall to support the bridge demolition.
Golden Hill Road activities:
Monday thru Friday:
- Continue truck traffic delivering bridge material and equipment.
- Continued construction work on the temporary trestle across the river.
Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084
Filed Under: Latest News
About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.