UPDATE: I-91 Rockingham Bridge construction schedule

The Vermont Agency of Transportation has begun replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of Sept. 25, 2017.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! PLEASE USE CAUTION!

I-91 activities:

Monday thru Friday – Daytime:

  • Begin saw cutting and removal of the concrete decking and floor beams
    from span 4 of the northbound bridge.
  • Begin prepping span 3 for removal and install lifting devices.

Golden Hill Road activities:

Monday thru Friday – Daytime:

  • Continue truck traffic delivering bridge material and equipment.
  • Continued construction work on the retaining wall under span 1.
  • Complete the temporary trestle across the Williams River.

Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084

Filed Under: Latest News

About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.

RSSComments (0)

Trackback URL

Comments are closed.