UPDATE: I-91 Rockingham Bridge construction
Press release | Mar 12, 2018 | Comments 0
© 2018 Telegraph Publishing, LLC
The Vermont Agency of Transportation is replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of March 12, 2018.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! PLEASE USE CAUTION!
Northbound bridge activities:
Monday thru Friday – Daytime:
• Continue work on preparation to cap Pier 1
• Continue work on Pier 2 shaft – prep for tier 4
• Continue work on Pier 3 – place tier 1; Prep for tier 2
• Continue work on I-91 Abutment 2
• Limited truck traffic on Golden Hill Road
Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084
Filed Under: Latest News
About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.