UPDATE: I-91 Rockingham bridge construction
Press release | Mar 20, 2018 | Comments 1
© 2018 Telegraph Publishing, LLC
The Vermont Agency of Transportation is replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of March 19, 2018.I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! PLEASE USE CAUTION!
Northbound bridge activities:
Monday thru Friday – Daytime:
• Continue work on preparation to cap Pier 1
• Continue work on Pier 2 shaft – place last tier
• Continue work on Pier 3 – backfill footing and continue prep for tier 2
• Begin drainage work at Abutment 1
• Continue work on I-91 Abutment 2
• Limited truck traffic on Golden Hill Road
Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084
Filed Under: Latest News
About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.
I’m seeing road signs (some of which are covered over) that make me think I-91 northbound traffic will, at some point in the future, be detoured through Chester via Rt. 11 to Springfield. Could you at the Telegraph get the highway folks to divulge why we are seeing these signs, and specifically what it will mean to Chester residents? Thanks,guys.